PHASE I – ground floor structure
– Brick – 20 m3 X 310 RON = 6 200 RON
– Sand – 2 lorries X 450 RON = 900 RON
– Cement – 2 pallets, X 700 RON = 1 400 RON
– Concrete – 5 m3 X 240 RON = 1 200 RON – Beams, plank = 1 000 RON
– Windows, doors = 6 000 RON
TOTAL = 16 700 RON (approx. 4000 EUR)
STAGE II – loft structure (wood) + roof
– Structure labor – 86 m2 X 60 EUR/m2 = 21 672 RON (5 160 EUR) (5 160 EUR)
– Metal tiles for roof – 128 m2 X 30 RON/m2 = 3 840 RON (915 EUR) (915 EUR)
TOTAL = 25 512 RON (approx. EUR 6 075)
PHASE III – exterior finishings (ground floor and loft) and interior (ground floor)
– Exterior – 35 RON/m2 X 240 m2 = 8 400 RON
– Loft walls OSB
– Polystyrene, plaster, washable exterior paint
Inside
– Sanitary and electrical installation – 4 000 RON
– Finishings and bathroom items (sink, tub/bath, toilet) – 4 000 RON
– Kitchen finishings – 4 000 RON
– Rendering, painting in living room and bedroom – 4 000 RON
– Laminate floor – 1 000 RON
TOTAL = 25 400 RON (approx. EUR 6 000)
PHASE IV – Utilities (hydrophore, central heating, radiators, septic tank, fences)
TOTAL = 16 800 RON (aprox. 4 000 EUR) TOTAL = 16 800 RON (approx. EUR 4 000)
TOTAL Project NDD = approx. EUR 20 000