Works’ status

At present:

- Architecture and structure resistance Projects have been paid for (3.100 RON)
- the Succession has also been concluded and paid for (900 RON)
- the bill for the Construction authorization has also been paid to the state (563 RON)
- we are working on obtaining the Construction authorization
- we are raising money for brick, cement and sand
- the materials necessary for masonry have been ordered: brick, cement, sand
- the materials necessary for masonry have been purchased: brick (20 m3), sand (10 tons) and adhesive for masonry (100 bags X 20 Kg)
- we are waiting for the Construction authorization in order to be able to immediately start the masonry work
- we received the Construction authorization
- the masonry works will start Friday, September 11
- the masonry works have been executed
- we purchased the necessary materials for building the concrete piers and of the flange (steel concrete, wire, plank)